Paragraphs in "Agreement Concerning A Joint Project For Planning, Design, Experiment, Preparation, Performance And Reporting Of Reactor Safety Experiments Concerning Containment Response" coded as SCIR

Displaying 1 - 12 of 12
Label Provision
Pre.13 A JOINT PROJECT FOR PLANNING, DESIGN, EXPERIMENT PREPARATION, PERFORMANCE AND REPORTING OF REACTOR SAFETY EXPERIMENTS CONCERNING CONTAINMENT RESPONSE (hereinafter called "the project").
Art.1.1x.bx #NAME?
Art.1.1x.cx -the possibilities offered by the Marviken reactor for such large scale experiments, already demonstrated in an international project concerning full scale containment tests performed during 1972 and 1973
Art.2.1x The purpose of this Agreement is to establish cooperation between the contracting parties in a project using jointly the Marviken reactor for certain safety experiments. The project covered by this Agreement comprises a joint programme for planning, design, experiment preparation, performance and reporting of reactor safety experiments concerning containment response.
Art.3.1x The scope of the project is to prepare and perform containment response tests at Marviken within the framework of an international cooperation.
Art.3.4x.b b) experiment preparation and performance of the test programme and
Art.3.4x.c c) data reduction and reporting of data and interpretation of results
Art.4.3 3. A committee, called the Technical Advisory Committee (TAC), shall be established. The committee shall be composed of senior technical experts. Each contracting party having a share of 20 % of the total budget shall have the right to designate two members and each contracting party having a share of less than 20 % shall have the right to designate one member. The committee has the authority to direct the project manager on technical matters within the scope, cost and time schedule of the programme. Differences in opinion between the TAC members shall be resolved by the vote following the same procedure as applies to the voting in the board. If the project manager considers a proposal from the TAC to lead to an increase in costs or to a prolongation of the time schedule, the matter shall immediately be brought by him to the attention of the board for decision. Pending the decision of the board, no action shall be taken by the project manager that may infringe upon the freedom of the board to decide. The project manager shall be in attendance at the meetings of the committee.
Art.4.5 5. AES undertakes to render the necessary technical and administrative services and to procure the material for implementation of the project. Legal acts relating to the carrying out of the project shall be performed by AES on behalf of the contracting parties.
Art.5.2 2. As no development work on instrumentation or other equipment is planned within the project it is vitally important that the board makes it their responsibility to supervise that only well proven and tested instrumentation and other equipment is used for the experiments. At the end of the preparation phase the board shall review the situation regarding the installed instrumentation and other equipment and its formal approval is required for the start of the experimental phase.
Art.5.3 3. At least after every second blowdown the TAC shall decide whether the blowdown and measurement conditions have concurred with the general descriptions of the experiments in the agreement and whether the information achieved is complete enough to be useful or if the experiments should be repeated. This decision shall be communicated to the board members immediately
Art.9.1.ax -Insurance of the equipment procured for the experimental work against fire, explosion, water pipe damage and/or damage to machinery, amounting to a total coverage of Skr 8 million.